The EVM Base Key Figures
The EVM key figures are a central element of EVM. The three most important key figures received new terms more than 20 years ago. In practice, however, you will probably come across the old EVM terms quite often. That is why I give you a short explanation here first.
In 1996, the EVMS criteria, which were taken over from the DoD Manual 5000.2R, were revised. They were then declared a national standard by the American Standards Institute/Electronic Industries Association (ANSI/EIA) in May 1998. This resulted in the Standard EIA-748 “Earned Value Management Systems (EVMS)”, which was then adopted by the DoD. This standard also changed the terms of the EVM basic performance figures.
- BCWS was renamed in PV (Planned Value)
- BCWP was renamed in EV (Earned Value)
- ACWP was renamed in AC (Actual Cost)
The main purpose of Earned Value Management is to analyze project performance. For this purpose, you only need four basic key figures, which you can easily determine from any good project planning and execution. All other metrics are based on these four metrics. Earned Value Management is based on these four key figures:
EV Earned Value or *(BCWP, Budgeted Cost of Work Performed)
PV Planned Value or (BCWS, Budgeted Cost of Work Scheduled)
AC Actual Cost or (ACWP, Actual Cost of Work Performed)
BAC Budget at Completion
* The old EVM key figure are sometimes still in use at large DoD contractors.
Performance Figures for Project Monitoring and Control
Variances
In the sections above you have learned about EVM basic key figures. Now let’s discover the performance figures for project monitoring and control.
CV Cost Variance CV=EV-AC or CV=BCWP-ACWP, CV% = CV/EV or CV/BCWP
SV Schedule Variance SV=EV-PV or SV=BCWP-BCWS, SV% = SV/ PV or SV/ BCW
VAC Variance at Completion VAC = BAC – EAC
(Favorable is positive, Unfavorable is negative)
Performance Indices
SPI Schedule Performance Index SPI=EV/PV or SPI=BCWP/BCWS
CPI Cost Performance Index CPI=EV/AC or CPI=BCWP/ACWP
(Favorable is >1.0, Unfavorable is <1.0)
Key Figures for Project Forecasts
With the following EVM key figures, you can look into the future and know early on what lies ahead for you. In this way, you can react in time and avoid major damage.
EAC – Estimate at Completion
EAC = AC + (BAC – EV) / 1 optimistic Method
EACCPI = AC + (BAC – EV) / CPI realistic Method
EACCPIxSPI = AC + (BAC – EV) / (CPI x SPI) pessimistic Method
(BAC – EV = Remaining Work)
ETC – Estimate to Complete
ETC = (BAC-EV)/1.0 optimistic Method
ETCCPI = (BAC-EV)/CPI realistic Method
ETCCPIxSPI = (BAC-EV)/(CPI x SPI) pessimistic Method
To Complete Performance Index
TCPIBAC = (BAC-EV) / (BAC-AC)
TCPIEAC = (BAC-EV) / (EAC-AC)
Percent Complete of overall Project
% Schedule PVcum / BAC x 100
% Complete EVcum / BAC x 100
% Spent ACcum / BAC x100
To % complete see also this article: How to Calculate the Earned Value of the Overall Project
The Earned Value Management Quick Access Card
With the following Earned Value Management Quick Access Card you have all formula summarized on one page quickly at a glance. If you think it still needs an important addition, then I am glad about a short message via the contact form.
Find Much More Details About Earned Value Management in This Book
Earned Value Management – Fast Start Guide
Discover How to Make Your Project Control Even More Effective and Bring More Transparency and Security to Your Projects.
This book is an indispensable manual for beginners in EVM but also for experienced Project Managers, Project Controls Specialists and Project Portfolio Managers who have the first contact with EVM.